Wed Nov 4, 12:18 PM ET
The board of the municipally owned CPS Energy has launched an investigation into how and when management because aware of the higher estimate.
Interim CPS Energy general manager Steve Barley, in a statement Tuesday, said an estimate that exceeds the preliminary total project cost of $13 billion is not acceptable.
The statement cited recent news reports about a $4 billion increase.
The utility seeks to expand STP, a two-unit nuclear complex about 90 miles southwest of Houston. The utility says the substantially higher preliminary cost estimate caused postponement last week of a proposed $400 million bond issue.
Names of the two workers were not released by the company.